±«Óătv

Apparatus

Large marble, adjustable support, runway, marker pen, metre rule, 50 cm rule, stop clock, safety goggles.

Large marble, adjustable support, runway, marker pen, metre rule, 50 cm rule, stop clock, safety goggles.

Method

  1. Set up the apparatus as shown in the diagram.
  2. With the marker pen mark a starting line, A, near the top of the runway.
  3. Likewise, mark a finishing line, B, near the bottom of the runway.
  4. Measure the distance between A and B with a meter rule. Record this distance in metres in a suitable table. This distance will remain unchanged throughout the experiment.
  5. Adjust the support so that the runway has a vertical height at A of 5 cm. Measure the distance with a 50 cm rule and record in the table.
  6. Place the marble at A. Release from rest and simultaneously start the stop clock.
  7. Stop the stop clock when the marble reaches B. Record the time taken in seconds in the table.
  8. Repeat twice more and then calculate the average time. Record in the table.
  9. Calculate the average speed using the equation: average speed = \(\frac{distance~travelled}{average~time~taken}\)
  10. Repeat the procedure for a total of 6 different vertical heights, increasing the height by 5 cm each time.
  11. Plot a graph of Average speed in m/s on the y-axis against Vertical height in m on the x-axis.

Safety

  • place an obstacle, such as a stool, to keep feet from underneath the runway making sure the marble doesn’t fall on someone’s foot;
  • make sure the marble doesn’t fall on to the floor and someone slips on it;
  • secure the runway with a clamp in the centre of the bench, so it doesn’t fall off on to someone’s foot;
  • wear safety goggles in case a marble hits someone in the eye.
Vertical height of runway in cmDistance travelled in mTime taken in s (1)Time taken in s (2)Time taken in s (3)Average time taken in sAverage speed in m/s
5 1.75
10 1.75
15 1.75
20 1.75
25 1.75
30 1.75
Vertical height of runway in cm5
Distance travelled in m1.75
Time taken in s (1)
Time taken in s (2)
Time taken in s (3)
Average time taken in s
Average speed in m/s
Vertical height of runway in cm10
Distance travelled in m1.75
Time taken in s (1)
Time taken in s (2)
Time taken in s (3)
Average time taken in s
Average speed in m/s
Vertical height of runway in cm15
Distance travelled in m1.75
Time taken in s (1)
Time taken in s (2)
Time taken in s (3)
Average time taken in s
Average speed in m/s
Vertical height of runway in cm20
Distance travelled in m1.75
Time taken in s (1)
Time taken in s (2)
Time taken in s (3)
Average time taken in s
Average speed in m/s
Vertical height of runway in cm25
Distance travelled in m1.75
Time taken in s (1)
Time taken in s (2)
Time taken in s (3)
Average time taken in s
Average speed in m/s
Vertical height of runway in cm30
Distance travelled in m1.75
Time taken in s (1)
Time taken in s (2)
Time taken in s (3)
Average time taken in s
Average speed in m/s

Graph

Graph showing vertical height on x axis and average speed on y axis

Error

The main cause of error in this experiment is reaction time when the person starts and stops the stop clock.

Error due to reaction time can be kept to a minimum by:

  • repeating the timing for each height three times and calculating the average time for the marble to roll down the runway;
  • ensuring that the time taken for the marble to roll down the runway is as long as possible. This can be done by:
    • making the distance between A and B as long as possible;
    • keeping the vertical height as small as possible, so that the marble doesn’t move too fast.

Conclusion

As the vertical height of the runway increases the average speed of the marble also increases, in line with our prediction.

However, we can say that the vertical height is not directly proportional the average speed as the line of best fit is not a straight line through the origin.